6. Loosen nut (A) and rotate barrel (B) to adjust length so
that the link lines-up with header bracket.
7. Install clevis pin (C) and secure with cotter pin (D).
8. Adjust link to required length for proper header angle
by rotating barrel (B). Tighten nut (A) against barrel. A
slight tap with a hammer is suf
fi
cient.
Figure 4.95: Mechanical Center-Link
CAUTION
Check to be sure all bystanders have cleared the area.
9. Press the HEADER UP switch (A) to raise header to
maximum height.
NOTE:
If one end of the header does
NOT
raise fully, rephase
the cylinders as follows:
a. Press and hold the HEADER UP switch until both
cylinders stop moving.
b. Continue to hold the switch for 3–4 seconds.
Cylinders are now phased.
Figure 4.96: GSL
169890
138
Revision A
Summary of Contents for M105
Page 8: ......
Page 28: ...SAFETY Figure 1 21 Safety Signs LH Side 169890 14 Revision A ...
Page 30: ...SAFETY Figure 1 23 Safety Signs RH Side 169890 16 Revision A ...
Page 40: ......
Page 87: ...OPERATOR S STATION 169890 73 Revision A ...
Page 88: ...OPERATOR S STATION 169890 74 Revision A ...
Page 89: ...OPERATOR S STATION 169890 75 Revision A ...
Page 90: ...OPERATOR S STATION 169890 76 Revision A ...
Page 91: ...OPERATOR S STATION 169890 77 Revision A ...
Page 92: ...OPERATOR S STATION Operating Information Screens 169890 78 Revision A ...
Page 94: ......
Page 299: ...MAINTENANCE AND SERVICING Fuse Box Decal Figure 5 169 Fuse Decal 169890 285 Revision A ...
Page 350: ......
Page 372: ......
Page 382: ......
Page 383: ......