CN3600 Setup & Operation Manual Revision : 6/2020
5
2. INSTALLATION
2.1 SHIPPING AND UNPACKING
Check machine and accessories and report any damage and/or omissions to
JAVELIN
MACHINERY
immediately.
2.2 LOCATING MACHINE
In addition to machine floor plan, room should be provided around the machine to allow
for
•
Ease of service
•
Loading of material onto mandrel
•
For stacking of raw & finished materials
See below (Fig. 2.2
for suggested layout. The machine should be located on a relatively
flat & solid floor that will support a machine weight of approximately 1600kgs
Fig. 2-2 Space Requirements
SAFETY MEASURES:
•
Non slip surface around machine
•
Hazard tape around designated area
•
Good safe housekeeping around machine.