IDS1000 Container Data Center
User Manual
3 Power-On Commissioning
Issue 01 (2014-3-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
19
Before the power-on of the container data center fire extinguishing system, check all the fire
extinguishing components one by one by following the preceding check methods and items.
----End
3.3 Hardware Power-On Commissioning
Prerequisites
You have completed the power-on check.
You have obtained the
Container Data Center Initial Configuration Guide
and
Container
Data Center Power-On Commissioning Guide
.
You have obtained the documents delivered with the fire extinguishing devices.
Procedure
Step 1
Switch on the input circuit breaker for the VESDA power box in the corresponding protected
zone. For details, see the
Container Data Center Initial Configuration Guide
and
Container
Data Center Power-On Commissioning Guide
.
Step 2
Complete the power-on commissioning for the VESDA. For details, see the delivered
VESDA documents.
If multiple VESDAs are configured in the protected zone, follow the preceding power-on
operations to power on their hardware.
Step 3
Switch on the input circuit breaker for the gas extinguishing controller in the corresponding
protected zone. For details, see the
Container Data Center Initial Configuration Guide
and
Container Data Center Power-On Commissioning Guide
.
Step 4
Turn on the main power and backup power switches for the controller to power on the gas
extinguishing controller.