For details about how to set the solenoid valve test mode, see the
Container Data Center
Initial Configuration Guide
.
1.
If the system is configured with one fire extinguishing cylinder and no fire extinguishing
power box is configured (fire extinguishing power module SJ-DYX-0607, with relays
and batteries). Ensure that the jumper state for JP7 is OFF (detecting faults). If the
jumper state is not OFF, adjust it to OFF.
Figure 3-4
Setting the test mode for the solenoid valve
2.
If the system is configured with two or more fire extinguishing cylinders and no fire
extinguishing power box is configured (mode of the fire extinguishing power module
SJ-DYX-0607, with relays and batteries). Ensure that the jumper state of JP7 is ON (not
detecting faults). If the jumper state is not ON, adjust it to ON
position to be set.
Figure 3-5
Setting the test mode for the solenoid valve
Step 4
Set the power-on delay for the solenoid valve.
Set the power-on delay for the solenoid valve from 25s to 30s, as shown in