Power-On Commissioning
3.1 Initial Configuration
Prerequisites
The container data center has been installed and passed installation tests.
You have obtained the
Container Data Center Initial Configuration Guide
for the
corresponding solution.
Before commissioning the fire extinguishing system, familiarize yourself with the
configurations of the fire extinguishing system and the layout of each component in the
corresponding solution. For details, see the
Container Data Center Initial Configuration
Guide
for corresponding solutions.
Procedure
Step 1
Set the output jumper mode of the single alarm (JP8), composite alarm (JP9), and general
fault (JP10) to passive output, as shown in