IDS1000 Container Data Center
User Manual
3 Power-On Commissioning
Issue 01 (2014-3-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
17
----End
3.2 Checking Before Power-On
Prerequisites
You have completed the power-on for the Power Supply and Distribution System and the
fire extinguishing power distribution box (PDB) in the container data center.
Before the power-on, ensure that you have been familiarized with the function and control
relationship of each circuit breaker in the Power Supply and Distribution System. For details
about the function and control relationship of each circuit breaker in the Power Supply and
Distribution System, see the corresponding descriptions in the
Container Data Center Initial
Configuration Guide
.
Procedure
Step 1
Configure and check the initial parameter settings of the fire extinguishing system by
referring to the
Container Data Center Initial Configuration Guide
.
For details about how to configure and check the parameters, see
Step 2
Check the cable connections of solenoid valves. Disconnect the control cables to solenoid
valves to prevent the fire extinguishing equipment from malfunctioning due to improper
manual operations.
Figure 3-8
Solenoid valve