14U in the rack, and the ISR 9096 chassis occupies 6U in the rack. Under normal circumstances,
the only reason for performing an installation is when you remove a complete chassis from its
location in an existing HP Cluster Platform. Note the following constraints when replacing a
chassis:
•
Ensure that the replacement of a chassis does not disrupt the proper ventilation, so that
ambient temperature is maintained for air intake at the front of the chassis and exhaust at
the chassis vents. All cable bundles must be routed according to the original design and
cable route planning for your model of HP Cluster platform.
•
Ensure that you label the origin and destination of all cables, including power cables, Ethernet
cables, and InfiniBand cables, if the cables are not already labelled.
Warning!
It is very important that you follow the original power distribution plan and connect the chassis
power supplies to the correct distribution strips within the rack. This will ensure that the power
draw is correctly distributed across the rack’s redundant power distribution units.
This section provides step-by-step instructions for installing the ISR 9XXX chassis. Two people
are required to remove the interconnect from its box and mount it in a rack, due to its weight.
4.4.1 Resources Required to Perform an Installation
The following materials and tools are required to mount the ISR 9XXX chassis into a rack:
•
Flat-blade screwdrivers of varying lengths and blade sizes, or an electric screwdriver with
a selection of bits.
•
Cross-point (Posidrive or Phillips) screwdrivers of varying lengths and blade sizes, or an
electric screwdriver with a selection of bits.
•
M6 cage nuts and a cage nut insertion tool.
•
10mm x M6 machine screws.
4.4.2 Mounting The Chassis in the Rack
You mount the ISR 9XXX interconnect with its ports facing the rear of the rack. The rail kit consist
of two each of the components shown in
Figure 4-8
.
Figure 4-8 ISR 9288 Interconnect Rail Kit
•
Two larger inner rails (top of
Figure 4-8
) provide a flange for the chassis to rest on.
•
Two smaller outer rails (bottom of
Figure 4-8
) attach to the larger rails to form a telescoping
rail unit.
•
16 machine screws (eight per pair of rails) are provided in the kit to secure the rails to each
other.
4.4 Mounting the ISR 9XXX in the Rack
59
Summary of Contents for Cluster Platform Express v2010
Page 10: ...10 ...
Page 18: ...18 ...
Page 28: ...28 ...
Page 38: ...38 ...
Page 68: ...68 ...
Page 92: ...92 ...
Page 106: ...106 ...
Page 110: ...110 ...
Page 116: ...116 ...
Page 122: ...122 ...
Page 124: ...124 ...
Page 132: ...132 ...