ECOLOGIC 30 | instructions for use, maintenance and installation |
June 2015
48
3.
Boiler connection instructions
To connect boiler ECOLOGIC 30 to central heating system you must check:
It is necessary to take into account the installations of non-return valve spring (or other
locking elements) which automatically prevent uncontrolled circulation of the heating
medium through the boiler by natural gravitational path.
Correct installation of pipelines of central heating (pipeline dimensions, air extraction, pipe
system functionality, adequacy of heating system according to boiler power).
Distribution units (pump functionality, closing valves functionality, electrical zone valves func-
tionality, mixed valves functionality…).
Ensured inlet of air into the space where ECOLOGIC 30 combustion device is installed. Inlet
must be executed in a manner, so that it cannot be closed and must, at any moment, enable
supply of fresh air – oxygen for burning into space. Unsuitable solutions are slightly opened
windows or open doors, supply of air through a duct along the flue from the roof is also un-
suitable.
Voltage of electrical connection for combustion device ECOLOGIC 30 must be 230 V / 50 Hz
(given in technical data for boiler ECOLOGIC 30).
Inspection of outlet of smoke gases – flue. Condition for connection is consent
from chimney
sweep
, with which a chimney sweep ensure suitability of the flue for combustion device ECO-
LOGIC 30.
In placing and connecting the combustion device to central heating system, the installer must adhere
to the following:
Boiler ECOLOGIC 30 must be positioned horizontally, in length and depth.
Distances, according to the enclosed drawing, must be regarded (see
figure 1
, page 7
).
In cases of older installation on return line to combustion device ECOLOGIC 30, a cleaning ele-
ment with closing valves is installed.
Boiler ECOLOGIC 30 is fitted with safety valve of 2.5 bar on return line. Installer must ensure
proper size of expansion container for volume of heating water in the system (size of expan-
sion container must be dimensioned minimum of 10 % of water volume in system "150 litres
of heating water in the system, minimum volume of expansion container must be 15 l". ex-
pansion container must be installed on combustion device ECOLOGIC 30 without closing ele-
ments.
A filling release tap must be installed on the right side of the boiler, on connection DN20 (see
figure 17,
page 49
).
Minimal pressure of heating water in boiler of 0.7 bar is ensured.
In case where there are many heating loops (two direct loops or mix loops for radiator heat-
ing, boiler heating, convector heating),
connection scheme nr. 3 (page 54)
is always used,
where it is necessary to use a hydraulic switch and pump on boiler loop, which is electrically
connected to cable "pump" from the boiler (see
figure 8,
page 13
).
Boiler must be fitted with pressure gauge for pressure of heating water in the boiler, i.e. on
pipeline before each closing valve (enable that the pressure gauge indicates pressure in the
Summary of Contents for Aqua ECOLOGIC
Page 32: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 32 Figure 12...
Page 41: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 41 service...
Page 42: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 42 service...
Page 43: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 43 service...
Page 44: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 44 service...
Page 45: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 45 service...
Page 52: ...AQUA ECOLOGIC instructions for use maintenance and installation September 2015 52...