10 FUNCTIONAL TESTS
10.1 INTRODUCTION
10
10 FUNCTIONAL TESTS 10.1 INTRODUCTION
10.1.1 DESCRIPTION
The purpose of this section is to demonstrate the procedures necessary to perform a complete functional test
of all the SPM hardware while also testing firmware/hardware interaction in the process. Since the SPM is
packaged in a drawout case, a demo case (metal carry case in which an SPM may be mounted) may be useful
for creating a portable test set with a wiring harness for all of the I/O. Testing of the relay during commissioning
using a primary injection test set will ensure that CTs and wiring are correct and complete.
Cycle power to SPM to clear lockout times that may occur during testing.
After testing is complete it is a good idea to zero all statistics.
The following equipment is recommended to test the SPM's functionality and calibration.
1.
3 phase variable ac test set (voltage and current)
2.
0 to 15 V DC voltage source (needed to test Exciter/Field volts or current inputs)
3.
Function generator (needed to test collector ring field application)
4.
Timer
5.
Multimeters
6.
Switch
NOTE
Summary of Contents for SPM Series
Page 2: ......
Page 4: ......
Page 10: ...vi SPM Synchronous Motor Protection Control GE Power Management TABLE OF CONTENTS...
Page 74: ...6 4 SPM Synchronous Motor Protection Control GE Power Management 6 2 STATUS 6 ACTUAL VALUES 6...
Page 120: ...C 2 SPM Synchronous Motor Protection Control GE Power Management C 1 WARRANTY APPENDIXC C...
Page 124: ...iv SPM Synchronous Motor Protection Control GE Power Management INDEX...
Page 125: ...GE Power Management SPM Synchronous Motor Protection Control NOTES...