ZP3 Fire Control Panel Installation, Commissioning and Maintenance Manual
Page 90
REV 11 (ISS 08/03/2010)
13. Para 12.4.4 - All internal components of the panel enclosure shall be left inside the enclosure
to ensure EMC compatibility. The panel shall remain locked with key removed during
operation.
14. Para 12.5.2 and CEA GEI 1-052 Para 5.2.3 - Under menu \setup\system config\AGV\ the AGV
should be defined enabled for partial short circuit check.
15. Para 12.5.2 - Loops must be wired in "class A" return loop configuration.
16. Para 12.5.2 - Isolators should be placed on the loop, such that no more than 32
detectors/callpoints may be isolated in the event of an open or short circuit on the loop. (It is
recommended that no more than 32 points are included in a zone).
17. Para 12.6 - The controls keyswitch should be left on.
18. Para 12.10.2 - The panel audible sounder shall be operated at full volume and not
suppressed.
19. EN54-2 annexure A - The commissioning key should be off.
20. Heat sensor elements required to conform to EN54 Part 5 Grade 1 must be set up to
sensitivity 2.
21. To meet the requirements of EN54-2 either as a sounder output (type C) or an output to fire
protection equipment (type G) the output must be monitored and hence a monitored output
accessory board should be used as opposed to a relay output accessory board or line device.
22. The facility in the Setup/Points/Settings/Smoke alert delay must not be used when setting up
to meet EN54-2.
23. The ZP3 panel approved to EN54 was tested using the internal power supply. Although option
is provided to supply power from an external power supply this should not be used if
compliance with EN54 is essential.
24. The ZP3 panel approved to EN54 was tested using 11 isolators in a ZP address loop. Although
option is provided to software select up to 16 isolators, a maximum of 11 should be used if
compliance with EN54 is essential.
25. The loop wiring must be shielded with the screens being effectively earthed.
26. Para 5.3.1 b) - Charge rate jumper JP6 must be linked to meet the requirements of EN54 if the
battery capacity exceeds 17Ah. See
Power supply and battery calculations
on page 50 for
more details.