MAINTENANCE PROCEDURE
MAINTENANCE
4-46
EVERY 100 HOURS MAINTENANCE
4
Maintenance for every 10 hours service should be carried out at the same time.
LUBRICATING SWING CIRCLE
4
(4 points)
1. Lower the work equipment to the ground.
2. Using a grease pump, pump in grease through the grease fit-
tings shown by arrows.
3. After greasing, wipe off any old grease that was pushed out.
Summary of Contents for PC600-7
Page 2: ...1 1 FOREWORD 11 ...
Page 4: ...FOREWORD FOREWORD 1 3 ...
Page 5: ...FOREWORD FOREWORD 1 4 ...
Page 18: ...2 1 SAFETY 12 ...
Page 22: ...SAFETY SAFETY LABELS 2 5 LOCATION OF SAFETY LABELS 2 ...
Page 28: ...SAFETY SAFETY LABELS 2 11 19 Jump start prohibited 09842 A0481 ...
Page 59: ...3 1 OPERATION 13 ...
Page 168: ...MACHINE OPERATIONS AND CONTROLS OPERATION 3 110 Boom operation Bucket operation ...
Page 211: ...4 1 MAINTENANCE 4 ...
Page 277: ...MAINTENANCE MAINTENANCE PROCEDURE 4 67 q Center frame A Important check points q Boom ...
Page 288: ...5 1 SPECIFICATIONS 15 ...
Page 291: ...6 1 ATTACHMENTS AND OPTIONS 16 ...
Page 299: ......