7.4
Loading by crane
Loads must only be attached and hoisted by an
expert / capable person.
Do not use damaged or in any other way
impaired lashing points.
Use only lifting gear and lifting tackle with suffi-
cient load bearing capacity for the weight to be
loaded. Minimum load bearing capacity of
lifting gear: see max. operating weight
Chapter 2 „Technical data“ on page 15
.
Always use appropriate lifting and lashing
means on the lifting and lashing points.
Use lifting and lashing gear only in the pre-
scribed direction of load application.
Lifting and lashing gear must not be damaged
by machine components.
When lifting the machine avoid uncontrolled
movements of the load. If necessary, hold the
load with guide ropes.
1.
Shut down the engine.
2.
8.2.2.1 „Engaging the articulation
.
3.
Fasten the lashing tackle at the marked
lifting points.
4.
Adjust the length of the lifting tackle in such
a way, that the crane hook is vertically
above the centre of gravity of the machine.
5.
Use a suitable cross-beam to prevent the
machine from being damaged.
Fig. 97
Loading/transporting the machine – Loading by crane
BW 213 D-5
130
Summary of Contents for BOMAG BW 213 D-5
Page 2: ...2...
Page 9: ...1 Introduction Introduction BW 213 D 5 9...
Page 14: ...Introduction Machine type plate and engine type plate BW 213 D 5 14...
Page 15: ...2 Technical data Technical data BW 213 D 5 15...
Page 20: ...Technical data Noise and vibration data BW 213 D 5 20...
Page 21: ...3 Concerning your safety Concerning your safety BW 213 D 5 21...
Page 63: ...4 Display and control elements Display and control elements BW 213 D 5 63...
Page 82: ...Display and control elements Outside of machine BW 213 D 5 82...
Page 83: ...5 Tests before taking into operation Tests before taking into operation BW 213 D 5 83...
Page 95: ...6 Operation Operation BW 213 D 5 95...
Page 124: ...Operation Emergency procedures BW 213 D 5 124...
Page 125: ...7 Loading transporting the machine Loading transporting the machine BW 213 D 5 125...
Page 133: ...8 Maintenance Maintenance BW 213 D 5 133...
Page 207: ...9 Trouble shooting Trouble shooting BW 213 D 5 207...
Page 217: ...10 Waste disposal Waste disposal BW 213 D 5 217...
Page 219: ...11 List of special tools List of special tools BW 213 D 5 219...
Page 220: ...Belt tension tester BOMAG No 079 947 09 Fig List of special tools BW 213 D 5 220...
Page 221: ......
Page 222: ......