99
Version C) Rail lines are formed during two passes of the seed drill
If sowing starts on the left side of the field
Possible flap
positions
Calculation result
Line No.
Resulting
rhythm
Left flaps
Right flaps
2
999
2
1
2
4
999
4
2
3
6
999
6
3
4
8
999
8
4
5
10
999
10
5
6
12
999
12
6
7
14
999
14
7
8
Example:
The structural width of the sprayer is 12 m, the structural width of the machine is 3 m.
Procedure: 12:3=4 → Resulting rhythm – green line in the chart
The picture shows that rail lines are formed during the second and third pass of the seed drill.
If the rail flaps are located on the other side of the seed bar, the procedure will be the same but sowing
starts on the right side of the field and thus rail lines will be formed on the right side of the seed drill.
Summary of Contents for FALCON 3
Page 6: ...Manual FALCON 3 4 6 8 6 99 ...
Page 20: ...Manual FALCON 3 4 6 8 20 99 6 3 HYDRAULIC DIAGRAM OF THE MACHINE ...
Page 77: ...Manual FALCON 3 4 6 8 77 99 ISO alarms ...
Page 78: ...Manual FALCON 3 4 6 8 78 99 Hydraulic alarms Regulation alarms ...
Page 79: ...Manual FALCON 3 4 6 8 79 99 ...
Page 80: ...Manual FALCON 3 4 6 8 80 99 Machine specific alarms ...
Page 81: ...Manual FALCON 3 4 6 8 81 99 ...
Page 82: ...Manual FALCON 3 4 6 8 82 99 ...
Page 83: ...Manual FALCON 3 4 6 8 83 99 ...