Manual
FALCON 3 | 4 | 6 | 8
25
│
99
6.6.2
Connecting the pressure hose
Connect the pressure hose (outer
⌀
22 mm) with the small quick coupling to the tractor distributor.
Connect this hose to the circuit giving priority to the oil supply.
Picture 8 – Pressure hose connection
6.6.3
Commissioning
-
When setting the required fan revolutions, the hydraulic oil must be warmed up.
-
When commissioning the hydraulic drive, the fan revolutions (working air pressure on the pressure gauge
in the hopper) must be set gradually.
-
Fan revolutions (pressure on the pressure gauge) are set by regulating the oil flow rate in the tractor.
-
If the hydraulic drive is started with cold oil, it is necessary to increase the motor revolutions gradually
before the oil warms up.
-
During commissioning and the first handover, the technician in charge of the handover must inspect all
connections of the hydraulic drive and measure pressure in the free drain
hose. He must record the
obtained results in the handover protocol.
Free drain to the
tractor tank must
be all time
connected, even if
fan is not working
Summary of Contents for FALCON 3
Page 6: ...Manual FALCON 3 4 6 8 6 99 ...
Page 20: ...Manual FALCON 3 4 6 8 20 99 6 3 HYDRAULIC DIAGRAM OF THE MACHINE ...
Page 77: ...Manual FALCON 3 4 6 8 77 99 ISO alarms ...
Page 78: ...Manual FALCON 3 4 6 8 78 99 Hydraulic alarms Regulation alarms ...
Page 79: ...Manual FALCON 3 4 6 8 79 99 ...
Page 80: ...Manual FALCON 3 4 6 8 80 99 Machine specific alarms ...
Page 81: ...Manual FALCON 3 4 6 8 81 99 ...
Page 82: ...Manual FALCON 3 4 6 8 82 99 ...
Page 83: ...Manual FALCON 3 4 6 8 83 99 ...