5
Start-up
Installation and operating instructions
30
Daikin/ROTEX A2 F
Oil condensing boiler A2 F
008.1546499_02 – 04/2018 – EN
2
Check all items of the "Checklist after start-up" (see
Chap. 5.2
).
3
Log the test results in the checklist.
Only if
all points
on the checklist can be answered with
Yes
may
the A2 F be started up.
5.2
Checklists for start-up
Checklist before start-up
1.
Is the A2 F properly installed in accordance with a permitted set-up variant and without any discernible damage?
yes
2.
When using a pressure unit: installation site additionally secured (sealed tray, filter cup made of metal)?
yes
3.
Combustion air supply secured?
yes
4.
Adequate ventilation and extraction in the heating room with limited ambient air-independent (separate flue gas/air supply
line) or ambient air-dependent operation?
yes
5.
Does the mains connection conform to regulations?
yes
6.
Is the mains voltage 230 V, 50 Hz?
yes
7.
If the DIP switches on the circuit board are set to match the equipment variant designed (see
Chap. 12.4
).
yes
8.
Flue gas line correctly connected with a consistent gradient (at least 3°), secured with suitable brackets and no leaks?
yes
9.
For renovation: heat distribution network flushed out? Sludge separator fitted in heating return flow?
yes
10.
Is the diaphragm expansion tank mounted according to specifications and of the requisite size?
yes
11.
Is the safety valve connected to a safe, free drain?
yes
12.
Has the quality of the filling water been checked and has any necessary water preparation been carried out?
yes
13.
System water pressure within prescribed range?
yes
14.
Boiler and heating system vented?
yes
15.
All sensors connected and correctly positioned?
yes
16.
Mixer group, mixer module and mixer circuit sensor (optional) correctly connected?
yes
17.
Room controller (optional) correctly connected to the PCB?
yes
18.
Oil connection installed according to specifications, expertly and correctly?
yes
19.
Oil tank sufficiently filled and oil valves opened?
yes
Tab. 5-3
Checklist before start-up
Only if all questions can be answered with "Yes" may the system be
started up.
Checklist after start-up
A
Is the heating circulation pump running, does the heater get hot?
yes
B
Is the oil conduit vented?
yes
C
Is the oil pressure within the permissible range?
yes
D
Has the resistance of the flue gas pipe been measured and is it higher than the minimum resistance?
yes
E
Have the burner settings been checked using a flue gas analyser and do the values lie within the stipulated range?
yes
F
Has the boiler cladding been re-installed after start-up?
yes
Tab. 5-4
Checklist after start-up
Only if all questions can be answered with "Yes" may the system be
handed over to the user/owner.
1
Fill out the supplied installation and instruction form as well as
the first pages of the operating manual together with the oper-
ator.