Operating Instructions
Insulated Conductor Rail System
SinglePowerLine Program 0813
BAL0813-0007-EN
www.conductix.com
translated document
page 54 of 108
Use the QR code ("click" or "scan") to see our animation
Mounting Hanger Clamps
.
6.4.3.3
Mount conductor rail
WARNING!
Secure components against falling!
Possible falling components must be determined in the customer analysis as part of the operator's risk
and hazard analysis.
→
The operator must take appropriate measures.
Requirements:
The hanger clamps are correctly mounted on the support structure.
Work steps:
→
Mount the conductor rails according to the project-specific documents (note the position of the phases and protective conductor).
→
Insert the first conductor rail at approx. 45° into the hanger clamp and clip it in (see Fig. 60). Ensure that the conductor rails
engage correctly and the hanger clamp covers the insulation above and below (see Fig. 61).
Fig. 60: Clip the rail into the hanger clamp
Fig. 61: The rail is clipped into the hanger clamp
→
Mount all conductor rails in the same way.