36
4.4
Installation of the components of the decentralized system
General notes on location and fastening
– Locate the system components so that:
– the distance between particular components is as short as possible
and the maximum admissible distance is not exceeded.
– they are freely accessible, with enough space for operation and main-
t en ance (
0,5 m minimum clearance around the components,
distance to floor at least 1 m
).
– The
booster pump
, the
silver ionization unit
, and the
connector box
must be installed only in a
location having a water drain
on the floor.
If, for any reason, this is not possible it is mandatory to provide
water
sensors
to safely interrupt water supply in case of leakage. Furthermore,
install the components in a location that prevents damage to material
assets in case of leakage.
–
Danger of damage!
Do not install the components in exposed locations
or locations with excessive dust load.
– The
booster pump
is designed for wall mounting while the
control unit
,
the
silver ionization unit
, and the
connector box
are designed for
direct fastening to the ventilation duct/monobloc
. Make sure the
construction (wall, pillar, housing etc.) to which the components are to
be mounted, offers a sufficiently high loadbearing capacity and is suit
able for the installation.
Caution!
Do not mount the components to vibrating parts
.
–
Use only the provided fastening material
to mount the various com-
ponents. If for some special reasons an installation with the supplied
fastening material is not feasible, choose a type of installation that is
equally stable.
Mounting profiles for direct
fastening to the monobloc
Z409
560 mm
500 mm
260 mm
400 mm
Important!
Mount the small cabinet (spray circle discharge) in
a way that the hoses (building side) between the housing lead-
throughs on the duct, and the corresponding connectors on the
small cabinet can be installed with a constant downslope.