33
24. Place the ceramic angle (one or two angles) on top of the ceramic
plate.
Important!
The topmost ceramic plate does not require a ceramic an-
gle.
Important!
Between the vertical sections with systemspecific interstice
the specially marked ceramic angle must be used. On systems with
two ceramic angles per plate at least one angle is systemspecific.
Repeat steps
18
to 24 until all ceramic plates are installed. Please observe
the installation sequence of the plate rows.
24
L = 300 mm
L = 400 mm
L = 300 mm
L = 500 mm
L = 300 mm
L = 300 mm
L = 700 mm
L = 100 mm
Install the upper flow sheets:
25. Cut the supplied rubber gasket band into pieces of the appropriate
length. Use the supplied hexagon socket screws M6x12 mm and the
washers to fix the upper flow sheets and the rubber gaskets to the
brackets already installed.
Important!
Between the vertical sections with systemspecific interstice
the upper flow sheet marked with a “
V
” must be used.
25
Install the ceramic angle