31
Install the ceramic plates
Note
: The installation of the ceramic plates takes place from the bottom to
the top and always starts with the two rear rows to the very left and right
(viewed in flow direction). Then all other rear rows (if present) are installed
and finally all front rows are mounted.
18. Insert the upper and lower plate sealings into the corresponding slots
of the vertical sections and push them to the top or to the bottom
respectively until they come to a stop (this fixes the plate sealings in
position).
Important!
The contact surfaces of the sealing plates must face the
protruding end of the ceramic plate mounted later.
Important!
No lower plate sealing must be installed at the rear ceramic
plates that require the installation of an anti-drip sheet (see step 21).
19. Carefully push the ceramic plate (chamfered part facing the bottom)
into the corresponding slot of one of the vertical sections, then tilt the
plate to the back and insert it into the slot of the other vertical section.
Align the ceramic element so that it protrudes for the same amount on
each side.
19
18
20. Insert in the lower flow sheet between the ceramic plate and the two
vertical sections (
this step must be carried out only for the lowest
ceramic element of a vertical row
).
Important!
Between the vertical sections with systemspecific distance
the specially marked lower flow sheet must be mounted.
20