Operation
The Condair Dual Hybrid Humidifier must be commissioned and op-
erated only by personnel familiar with the unit and adequately qualified
for the task
. Ascertaining the qualification is the customer’s responsibil
-
ity.
5.1
Introduction
The Condair Dual Hybrid Humidifier is operated via the control unit. The
control unit provides the following display and control elements:
1 Display
(5x7 dot matrix, 2x16 characters)
2
<
M
>
key (menu key)
3
<
▲
>
key (arrow key up)
4
<
▼
>
key (arrow key down)
5
<
E
>
key (entry key)
6 “Error” indicator (red LED)
7 “Humidification on” indicator
(green LED)
8
<I/O>
key (power switch)
5.2
Commissioning for daily operation
The following description outlines the commissioning procedure for daily
operation. It is assumed that firsttime commissioning has been carried out
properly by the service technician of your Condair supplier. Proceed as fol-
lows to
prepare the Condair Dual Hybrid Humidifier for operation
:
• Check the installation and all system components for damage.
Caution! Do not put the system into operation in case of damaged
installations or system components.
•
Make sure the ceramic plates are correctly located and properly
sealed.
Caution! Put the system into operation only if the above require
-
ments are met without fail.
•
Set the mains supply service switch
(power supply to control unit) to
“
On
”.
•
First set the power switch
of the control unit to “
I
”,
then open the
shut-off valve
of the water supply conduit. The control system now
carries out a basic system test while the “Humidification on” and “Error”
indicators light up. Once the test is completed the drain valve opens for
approximately 20 seconds (flushing of the permeate conduit).
test