8.3
Verifying the communication
SEMOD172108-24 v10
To verify that the communication is working a test/analyzing tool, for example
ITT600, can be used.
Verifying redundant IEC 61850-8-1 communication
Ensure that the IED receives IEC 61850-8-1 data on the selected Ethernet ports.
Browse in the local HMI to
Main menu/Diagnostics/Communication/Ethernet
status/Access point/APStatusRedundant/RCHLCCH:1
and check that
ChARedStatus and ChBRedStatus are shown as
Ok
. Remove the optical
connection to one of the Ethernet ports. Verify that either signal status (depending
on which connection that was removed) is shown as
Error
and the that other signal
is shown as
Ok
. Be sure to re-connect the removed connection after completed
verification.
Section 8
1MRK 505 378-UEN A
Establishing connection and verifying the IEC 61850 communication
72
Line differential protection RED670 2.2 IEC
Commissioning manual
Summary of Contents for RED670 Relion 670 series
Page 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Page 2: ......
Page 18: ...12 ...
Page 36: ...30 ...
Page 68: ...62 ...
Page 72: ...66 ...
Page 108: ...102 ...
Page 278: ...272 ...
Page 282: ...276 ...
Page 288: ...282 ...
Page 306: ...300 ...
Page 307: ...301 ...