1.
Operate value measurement
The current restraining value has also to be measured or calculated and the
influence on the operation has to be calculated when the testing of the operate
value is done.
11.8.1.3
Overcurrent feature with voltage restraint
SEMOD56488-44 v5
Procedure
1.
Connect the test set for injection of three-phase currents and three-phase
voltages to the appropriate current and voltage terminals of the IED.
2.
Inject current(s) and voltage(s) in a way that relevant measured (according to
setting parameter
CurrentInput
and
VoltageInput
) currents and voltages are
created from the test set.
Overall check in principal as above (non-directional overcurrent feature)
3.
Operate value measurement
The relevant voltage restraining value (according to setting parameter
VoltageInput
) has also to be injected from the test set and the influence on the
operate value has to be calculated when testing of the operate value is done.
4.
Operate time measurement
Definite times may be tested as above (non-directional overcurrent feature).
For inverse time characteristics the START value (to which the overcurrent
ratio has to be calculated) is the actual pickup value as got with actual
restraining from the voltage restraining quantity.
11.8.1.4
Overcurrent feature with directionality
SEMOD56488-60 v5
Please note that the directional characteristic can be set in two different ways either
just dependent on the angle between current and polarizing voltage (setting
parameter
DirPrinc_OC1
or
DirPrinc_OC2
set to or in a way that the operate
value also is dependent on the angle between current and polarizing voltage
according to the I · cos(
F
) law (setting parameter
DirPrinc_OC1
or
DirPrinc_OC2
set to I · cos(
F
). This has to be known if a more detailed measurement of the
directional characteristic is made, than the one described below.
Procedure
1.
Connect the test set for injection of three-phase currents and three-phase
voltages to the appropriate current and voltage terminals of the IED.
2.
Inject current(s) and voltage(s) in a way that relevant measured (according to
setting parameter
CurrentInput
and
VoltageInput
) currents and voltages are
created from the test set.
3.
Set the relevant measuring quantity current to lag or lead (lag for negative
RCA angle and lead for positive RCA angle) the relevant polarizing quantity
voltage by an angle equal to the set IED characteristic angle (rca-dir) when
forward directional feature is selected and the
CTstarpoint
configuration
parameter is set to
ToObject
.
1MRK 505 378-UEN A
Section 11
Testing functionality by secondary injection
Line differential protection RED670 2.2 IEC
213
Commissioning manual
Summary of Contents for RED670 Relion 670 series
Page 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Page 2: ......
Page 18: ...12 ...
Page 36: ...30 ...
Page 68: ...62 ...
Page 72: ...66 ...
Page 108: ...102 ...
Page 278: ...272 ...
Page 282: ...276 ...
Page 288: ...282 ...
Page 306: ...300 ...
Page 307: ...301 ...