82 Planning the electrical installation
Customer wiring
The insulation monitoring device can be connected to external systems. See the circuit
diagrams delivered with the inverter.
Start-up
See chapter
More information
•
Circuit diagrams delivered with the inverter
•
Manufacturer’s operating manual of the insulation monitoring device
Implementing positive or negative pole grounding
(oF282 and +F283)
Some solar module types require positive or negative grounding. Make sure that the
optional positive (+F282) or negative (+F283) grounding method is suitable for the solar
modules that you are using.
Ground the panels during long maintenance breaks if the panel type requires it.
Limiting the conducted disturbances with the EMC filter
(E216) in low-voltage TN (grounded) networks
The optional EMC filter (+E216) can be installed at the network-side of the low voltage
transformer to limit the conducted disturbances to other equipment connected to the
network. The filter has capacitors connected to ground and is not suitable for IT
(ungrounded) networks. Ensure that the network owner and operator allows the
installation of this kind of a filter. The filter must always be installed according to local
regulations.
Instructions for inverters delivered without input DC
fuses (0F291)
If the standard input DC fuses are not suitable for the customer application, the inverter
can be delivered without input DC fuses (0F291). In this case, install appropriate
DC fuses to protect the inverter DC circuit and the DC input cables in a short-circuit
situation. Protect
the positive and negative poles of an input with separate fuses. The
power loss of a fuse may never exceed 25 W.
The table in section
Fuses for inverters delivered without input DC fuses (0F291)
(page
) shows the rated DC current for selecting the input DC fuses.
Mechanical installation of the input DC fuses
Use M10 or M12 bolts and nuts to connect the fuses to the busbars.
Summary of Contents for PVS800-57-0100kW-A
Page 1: ...ABB solar inverters Hardware manual PVS800 57 central inverters 100 to 1000 kW ...
Page 4: ......
Page 22: ...20 Safety instructions ...
Page 64: ...62 Operation principle and hardware description ...
Page 74: ...72 Mechanical installation ...
Page 90: ...88 Electrical installation PE PE PE ...
Page 124: ...122 Maintenance ...
Page 152: ...150 Dimension drawings Frame R7i 3AUA0000083128 ...
Page 153: ...Dimension drawings 151 AC output 3AUA0000083128 ...
Page 154: ...152 Dimension drawings 3AUA0000083128 One DC input Four DC inputs ...
Page 156: ...154 Dimension drawings R8i 8 DC inputs option 8H382 3AXD50000016935 ...
Page 157: ...Dimension drawings 155 R8i AC output terminals 3AXD50000016935 ...
Page 165: ...Dimension drawings 163 2 R8i AC output terminals 3AXD50000015007 ...
Page 173: ...Dimension drawings 171 3 R8i AC input terminals 3AXD50000015006 ...
Page 178: ...176 Dimension drawings ...
Page 180: ...Contact us www abb com solar 3AUA0000053689 Rev H EN EFFECTIVE 2014 07 09 ...