Start-up 99
8
Start-up
Contents of this chapter
This chapter describes the start-up procedure of the inverter. It also gives some advice for
operation.
Start-up procedure
The functioning of the inverter is first tested in the local control mode with the control panel
(CDP312R). Thereafter, the control program parameters are set. The start-up procedure is
described step-by-step in the table below.
SAFETY
WARNING!
Obey the safety instructions during the
installation and start-up procedure. See chapter
Only qualified electricians are allowed to install and start-up the
inverter.
PRIMARY AND AMBIENT CONDITION CHECKS
Check that the mechanical and electrical installation of the
inverter is OK. See chapter
Check that the insulation of the assembly is OK. See section
Checking the insulation of the assembly
, page
Note:
If the insulation is not OK, the
optional insulation resistance
monitoring (Q954, +Q976 or
+Q981) cannot be tuned properly.
Check that the ambient conditions for start-up, temperature and
humidity level is within the limits. See section
,
page
Note:
Depending on the humidity level or temperature, it can be
necessary to use cabinet heaters continuously for a longer time
before start-up.
Summary of Contents for PVS800-57-0100kW-A
Page 1: ...ABB solar inverters Hardware manual PVS800 57 central inverters 100 to 1000 kW ...
Page 4: ......
Page 22: ...20 Safety instructions ...
Page 64: ...62 Operation principle and hardware description ...
Page 74: ...72 Mechanical installation ...
Page 90: ...88 Electrical installation PE PE PE ...
Page 124: ...122 Maintenance ...
Page 152: ...150 Dimension drawings Frame R7i 3AUA0000083128 ...
Page 153: ...Dimension drawings 151 AC output 3AUA0000083128 ...
Page 154: ...152 Dimension drawings 3AUA0000083128 One DC input Four DC inputs ...
Page 156: ...154 Dimension drawings R8i 8 DC inputs option 8H382 3AXD50000016935 ...
Page 157: ...Dimension drawings 155 R8i AC output terminals 3AXD50000016935 ...
Page 165: ...Dimension drawings 163 2 R8i AC output terminals 3AXD50000015007 ...
Page 173: ...Dimension drawings 171 3 R8i AC input terminals 3AXD50000015006 ...
Page 178: ...176 Dimension drawings ...
Page 180: ...Contact us www abb com solar 3AUA0000053689 Rev H EN EFFECTIVE 2014 07 09 ...