6.22. Install Grain Band Posts
This sections describes how to plan the installation of grain band posts, and how to install them when you begin
installing plenum sheets.
Install grain band posts at the same time as plenum sheets are installed.
1. Familiarize yourself with the grain band post pattern required for the size of bin you are assembling. (See
).
2. Using plenum sheet locators, position plenum sheets on rafters.
3. Locate the circular row of plenum sheet “notches” as shown in
4. Place the grain band posts on top of plenum sheets.
5. Center grain band posts at each level in line with the notches.
6. Bolt the grain band posts to the plenum sheets using the bolts and nuts specified for attaching plenum
sheets to rafters.
Figure 31.
Grain Band Post Layout Patterns
24’ [7.31 m] Post Layout Pattern
27’ [8.23 m] Post Layout Pattern
30’ [9.14 m] Post Layout Pattern
36’ [10.97 m] Post Layout Pattern
EASYDRY® WIDE-CORR CENTURION® GRAIN BIN – GRAIN BIN DRYER