![Westeel EasyDry Wide-Corr Centurion 24 Series Скачать руководство пользователя страница 144](http://html.mh-extra.com/html/westeel/easydry-wide-corr-centurion-24-series/easydry-wide-corr-centurion-24-series_original-instructions-manual_959902144.webp)
144
250050 R1
6.46.2 Sampling Hatch (30' and 36') Installation
Figure 113.
Sampling Hatch (30' and 36') Detail
FIELD DRILLING TO MATCH FOUR CORNER HOLES IN
HATCH IS REQUIRED IN WALL SHEETS
DIRECTLY ABOVE AND BELOW HATCH
PLACE HATCHBEHIND
THE SHORT WALL SHEETS
SAMPLING HATCH
(232958)
3/8” x 1” BOLT,
FLAT WASHER & NUT
DOUBLE PUNCHED
SHORT WALL SHEET
(194783) BOTH SIDES
NOTES
:
FOR EASIEST ASSEMBLY, INSTALL SAMPLING HATCH
BEFORE INSTALLING WALL SHEET IN TIER BELOW
Important
Inner hatch board must be closed and latches completely engaged before filling. Failure and collapse of
the bin could result if bin is filled without properly closing inner hatch board.
6.46.3 Walk-In Door Installation
Install the door from the inside of the bin using 3/8" x 1-½" bolts. The door should overlap the top spacer sheet
as shown below. Place caulking on the top spacer sheet above and below the row of holes where it will meet
with the door frame. The bottom spacer sheet overlaps the door from the inside as shown. Place caulking above
and below the row of holes where it will meet the door frame. Both spacer sheets must be installed below the
door if auger chute and full floor aeration are used. Locate door tie-back to secure door in open position.
EASYDRY® WIDE-CORR CENTURION® GRAIN BIN – GRAIN BIN DRYER