Diesel Gen-set Operation Instructions
32
Chapter 6 Installation of the Gen-set
I. Preparations before installation
1. Unpacking of the Gen-set
Before unpacking, clean dust and check if body of the case is damaged or not at first.
Then, check case number and quantity and do not damage the machine during
unpacking. During unpacking, top plate shall be removed first and side plates shall be
removed latter. Followings are necessary after unpacking:
1) Checking of Gen-set nameplate and checking if the Gen-set meets ordering
requirements or not;
2) Making an inventory on the Gen-set and its accessories in accordance with packing
list of the Gen-set;
3) Checking if the Gen-set and its accessories are damaged or rusted or not;
The Gen-set after being unpacked must be positioned horizontally and flanges and
various joints must be sealed, in order to prevent intrusion of moisture and foreign
objects.
2. Preparations for equipment installation
Before installation of the Gen-set, relevant equipment and tools (e.g. crane, forklift
and wrench, etc.) shall be prepared as per construction scheme.
II. Requirements for installation of the Gen-set
1. Size of equipment room
1) Size of equipment room of the Gen-set shall meet space requirements for
installation, operation and maintenance of the Gen-set.
2) An opening for transporting of the Gen-set shall be reserved in the equipment room,
in order to ensure that the Gen-set can be moved to its installation position. At least a
2500×2000mm opening for transportation shall be reserved for 10~50kW series