4.5 - GREEN MACHINE
™
- North America - Installation, Operation, Maintenance, & Troubleshooting Manual
Chapter 1: GREEN MACHINE
™
Installation
Page 22
1.3
Installing the Legs on the GREEN MACHINE
1.
Support the GREEN MACHINE with a forklift or a set of saw horses so the legs can be
installed.
2.
Install the 4 legs on the GREEN MACHINE
. The four 3/8” carriage bolts for each leg MUST BE
INSTALLED AND TIGHTENED IN THE SEQUENCE INDICATED ON
Figure 1-1
.
3.
All the carriage bolts must be installed so the head of the bolt is flush with the base as
shown.
Figure 1-1: Bolting sequence to attach legs to the GREEN MACHINE base