Chapter 6: Testing & Startup
Page 75
Chapter 6: Testing & Start-Up
6
Post-Installation GREEN MACHINE Testing & Start Up
6.1
VST Control Panel Initial Start-Up Power:
When the power is turned ON to the VST Control Panel, the Main Screen will show on the PLC
with the label
GM DISABLED
–
ENTER CODE
. See
Figure 6-1
. The CODE was initiated to prevent
the electrical contractor from starting the GREEN MACHINE before the Start-Up was completed.
The Start-Up can be completed with the GM DISABLED. The CODE to the VST Control Panel
must be entered before the GREEN MACHINE can become operational. The CODE will be
supplied to the Start-Up Contractor via e-mail after Appendix B is submitted online.
Figure 6-1: Main Screen with the GM DISABLED
–
ENTER CODE