Chapter 7: Maintenance Procedures
7
Maintenance Overview
•
VST recommends conducting Maintenance on the GREEN MACHINE annually to make sure all
the components are in good working order. If the annual maintenance is not conducted, there
is a possibility the GREEN MACHINE may not be operating properly.
•
The Vacuum Pump and Control Valves are the only components with moving parts in the GREEN
MACHINE; therefore, it requires very little maintenance.
•
All replacement parts must be from VST’s recommended replacement parts list located in
Chapter 9: Replacement Procedures Section.
•
If the GREEN MACHINE is not functioning properly consult Chapter 8: Troubleshooting Section to
determine which component may need to be repaired or replaced.
•
Sections that will be covered in this Chapter:
7.1
Maintenance Procedures
7.2
Recommended Replacement Parts
7.3
Functionality Test
7.4
Pressure Sensor Verification Test
7.5
Rubber Flange Sleeve Replacement
7.6
Cleaning the Control Valves
7.7
Check the Air Outlet for Liquid Condensation
7.8
Separator Check Procedure
7.1
Maintenance Procedures
1.
At the VST Control Panel Main Screen, check to make sure there are no alarms.
See Figure 7-1
.
If there are alarms, repair the item causing the alarm (See Chapter 8: Troubleshooting)
before proceeding.
2.
VST has recommended spare parts that might be needed when conducting
Maintenance.
See Section 7.2.
3.
Conduct a Functionality Test:
See Section 7.3.
The Functionality Test will verify the GREEN MACHINE is operating properly.
•
If the Functionality Test Passes, go to Step 3.
•
If the Functionality Test does not Pass (See Chapter 8: Troubleshooting Procedures)
4.
Conduct a Pressure Sensor Verification Test:
See Section 7.4.