4.5 - GREEN MACHINE
™
- North America - Installation, Operation, Maintenance, & Troubleshooting Manual
Chapter 9: Replacement Procedures
Page 166
9.5.2
Replacing the Rubber Flange Sleeve
See Figure 9-13.
1. Insert a new rubber flange sleeve and slide the motor back to its original position.
•
Make sure the motor-side drive coupling is snug (not tight) against the rubber flange
sleeve.
2. Replace any shims that moved while moving the motor.
3. Re-install and tighten the 4 motor mounting bolts to the base plate. Make sure the Motor
Shaft and Vacuum Pump shafts are in alignment.
4. Re-install the 2-bolts holding the Internal Junction Box stand to the GREEN MACHINE
base.
5. Re-install the fan guard over the coupling flanges.
6. Put the cover on the GREEN MACHINE and lock the hasps.
7. Remove the lock(s) and tags from the lockout & tagout.
8. After the work is completed, turn ON power to the VST Control Panel. The GREEN
MACHINE is now operational.
Figure 9-13: Replacing the Rubber Flange Sleeve