Chapter 6 Installing the EX2 expansion module
88
BAS-APG001-EN
Figure 46. Mounting the metal-enclosure EX2
AC-power wiring
Use 16 AWG copper wire for ac-power wiring. All wiring must comply
with National Electrical Code and local codes. Use a UL-listed Class 2
power transformer supplying a nominal 24 Vac. The transformer must be
sized to provide adequate power to the EX2 module (10 VA) and outputs
(a maximum of 6 VA per binary output).
Please read the warnings and cautions before proceeding.
WARNING
Hazardous voltage!
Before making line voltage electrical connections, lock open the supply-
power disconnect switch. Failure to do so could result in death or seri-
ous injury.
WARNING
Hazardous voltage!
Make sure that the 24 Vac transformer is properly grounded. Failure to
do so could result in death or serious injury.
Содержание Engineered Smoke Control System
Страница 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Страница 2: ......
Страница 3: ...BAS APG001 EN September 2006 Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Страница 6: ......
Страница 12: ...Contents vi BAS APG001 EN ...
Страница 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Страница 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Страница 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Страница 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Страница 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Страница 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Страница 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Страница 104: ...Chapter 6 Installing the EX2 expansion module 92 BAS APG001 EN Figure 49 I O bus wiring example 2 ...
Страница 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Страница 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Страница 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Страница 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Страница 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Страница 154: ...Appendix A References 142 BAS APG001 EN ...
Страница 155: ......