33
TRAK Machine Tools
Southwestern Industries, Inc.
TRAK TMC Mills with ProtoTRAK RMX CNC Safety, Installation, Maintenance, Service & Parts List
Installation Checklist
7.
Reinstall rear coolant bracket which prevents leaking of coolant through the rear of the
machine. Hardware provided on coolant tank.
8. Wire up the auger, coolant pump and coolant wash pumps per section 5.1.8.
9. Re-attach the Z motor power and encoder cable if it was disconnected during shipment. Make
sure to thread the cables on all the way.
10. Install the X and Y EHW’s if
they were sold with the machine. Reattach the cable carriers to
the bottom portion of the EHW trough.
11. Turn on the power to the machine. Verify the lube pump cycles 1 time when machine is turned
on.
12. Adjust air pressure on the main air regulator to 90 psi. Adjust air regulator for the spindle
cartridge to 7 psi.