34
TRAK Machine Tools
Southwestern Industries, Inc.
TRAK TMC Mills with ProtoTRAK RMX CNC Safety, Installation, Maintenance, Service & Parts List
Installation Checklist
13. Prior to setting the machine down, thread each leveling bolt down
approximately 1.25”
as
measured from the bottom of the leveling bolt to the bottom of the casting.
Prior to adjusting the final level on the machine, slide the coolant tank under the machine with the
coolant chutes in place. Make sure the slots on the chutes are all the way up as shown. Now lower
the chutes to confirm they reach the coolant tank and are flush or maybe a little of the way down
inside the coolant tank. If the chutes do not reach the tank, then lower the machine with the
leveling screws. This will allow the coolant/chip chutes to come down and minimize any coolant
splashing.
Note -
One of the coolant/chip chutes will need to be reattached as it is shipped separately with
the machine.
14. Check the level of the machine. The machine should be level to within 0.0005"/12 inches front
to back and 0.0005"/12 inches side to side. Adjust leveling feet as necessary to adjust for the
spindle tram should it be out of spec.