Commission the plant line by line.
And these are the individual steps to be followed:
Step
Procedure
Notes
1
Make addressing of the line couplers.
2
Commissioning RXB/RXL room controller
and Synco room thermostats
RDG/RDF/RDU using the service tool
OCI700.1
1. Select the application and adjust the
setting values according to HVAC
planning.
2. Set RXB/RXL communication data
points according to the Synco
TM
Planning and Commissioning Protocol
C3127.
3
Commissioning the RMB795B central
control unit
1. Set configuration and setting values
according to the configuration diagram.
2. Make the wiring test.
3. Set the RMB795B communication data
points according to the Synco
TM
Planning and Commissioning Protocol
C3127.
4. Run search of device supervision
5. Compare the identified devices against
the planning documentation.
6. Exit
commissioning
4 Commissioning
additional
devices
Line coupler filter tables,
QAW740, RMU7xx,
RMH760, etc.
5
Check setpoints and setting values, time
programs, calendar, etc.
Check building functions.
Night cooling, fire
shutdown, smoke
extraction, heating
demand, refrigeration
demand, etc.
6
Generate the commissioning protocols.
7
Do the final work, handover, instructions to
the customer / plant operator.
Commissioning