Central control unit RMB795B
CE1P3122en
Building Technologies
Engineering and commissioning guidelines
18.01.2012
These are the individual steps to be followed when completing the Synco
TM
planning and commissioning protocol "Communication" (C3127):
Step
Procedure
Notes
1
Enter general information about the plant
and the device types
2 Press
button
Menu > Update fields
Fields that need not be
completed appear with
hatched lines
3
Enter the device addresses of all users
To be adopted from the floor
plans
4
Define the names and room numbers of all
users and room groups
While observing the floor
plans
5
Define the bus power supply according to
the supply concept
Refer to Data Sheet N3127,
"KNX bus"
6
Define clock time operation
Autonomous, slave, master.
7
Enter the geographical zone address
To be adopted from the floor
plans
8
Define the QAW zone (apartment)
According to the room group
assignments
9
Define the time switch zone
According to customer needs
10
Define holidays / special day zones
Ditto
11
Define the outside temperature zones
According to HVAC plant
12
Define the refrigeration distribution zones
on the consumer side
Ditto
13
Define the refrigeration distribution zones
on the generation side
Ditto
14
Define the heat distribution zones on the
consumer side
Ditto
15
Define the heat distribution zones on the
generation side
Ditto
Observance of the points listed below contributes to trouble-free and effective
commissioning:
•
Early coordination of installation of devices and KNX bus with the project leader
or installer responsible for the project
•
Correct installation of the devices in accordance with the mounting instructions
•
Observance of KNX bus installation instructions
•
Setting a commissioning date on which the installation will be completed and all
forms of energy (electricity, heat and refrigeration) will have to be available
Complete planning and
commissioning protocol
Installation