Publication DNET-UM072C-EN-P - July 2004
Determine Power Requirements
4-13
Section 2 = 140m (2.14A)
Section 1 is overloaded because the total current exceeds the maximum
current (2.85A > 2.14A).
Section 2 is operational since the total current does not exceed the maximum
current (0.75A < 2.14A).
Balance the system by moving the power supply toward the overloaded section
(section 1). Then recalculate each section.
IMPORTANT
Section 1 + Section 2 < 3.6A. This is < 4A for
NEC/CECode compliance.
Results
Содержание H Series
Страница 135: ...DeviceNet Media Design and Installation Guide...
Страница 144: ...Publication DNET UM072C EN P July 2004 Table of Contents iv...
Страница 170: ...Publication DNET UM072C EN P July 2004 1 26 Get Started Notes...
Страница 194: ...Publication DNET UM072C EN P July 2004 2 24 Identify Cable System Components Notes...
Страница 212: ...Publication DNET UM072C EN P July 2004 3 18 Make Cable Connections Notes...
Страница 238: ...Publication DNET UM072C EN P July 2004 4 26 Determine Power Requirements Notes...
Страница 248: ...Publication DNET UM072C EN P July 2004 5 10 Correct and Prevent Network Problems Notes...
Страница 250: ...Publication DNET UM072C EN P July 2004 A 2 Understand Select NEC Topics Notes...
Страница 263: ......
Страница 267: ...Isysnet Serial Bus System Selection Guide Pneumatic...
Страница 287: ...H Series Fieldbus DeviceNet Adapters PSSCDM12A PSSCDM18PA User Manual...