Ds230_03a_oi_e.doc / Jun-15
Page 88 / 100
8.7.
Completion of Commissioning
Finally all application-dependent Parameters should be checked for plausibility again. The digital
outputs and relays can be tested for their correct behavior by using the parameter 058 "Output
Action" from the menu "Switching Menu".
The safety-related relay output opens in case of failures or if a programmed switching condition (see
chapter
) is reached. Further the contact will be open, if the unit is in the de-energized state.
It is imperative to test the function of the relay and the evaluation in the target device finally!
The user of the equipment is responsible for ensuring all relevant
parts of the system to a safe state, when the relay contact is open.
After commissioning, the unit state “Operational Mode” must be left by setting the slider 3 of the
DIL switch back to its „ON“ position. For a normal operation always all 3 sliders of the DIL switch
must be set to „ON“.
„Programming Mode“ (DIL switch) only for start-up
Set all DIL switch sliders to „ON“ after start-up
Protect the DIL switch sliders after start-up
(e. g. by covering with an adhesive tape)
Normal operation is only permitted when the yellow LED is permanently off
Содержание DS230 Series
Страница 10: ...Ds230_03a_oi_e doc Jun 15 Page 10 100 4 3 DS236 Block Diagram 4 4 DS236 Connections...
Страница 11: ...Ds230_03a_oi_e doc Jun 15 Page 11 100 4 5 DS240 Block Diagram 4 6 DS240 Connections...
Страница 12: ...Ds230_03a_oi_e doc Jun 15 Page 12 100 4 7 DS246 Block Diagram 4 8 DS246 Connections...
Страница 99: ...Ds230_03a_oi_e doc Jun 15 Page 99 100 11 1 Dimensions inclusive BG230 at front Front Rear DS230 BG230 option...
Страница 100: ...Ds230_03a_oi_e doc Jun 15 Page 100 100 12 Certificate...