50
|
PROVENO E
Rev. 1.2 (24.08.2016)
Installation
5.2.4. Subsurface frame cast into the fl oor
Installation frames are mounted according to the installation drawing, with the help of distance guides
supplied with the delivery. The frames must be installed in a horizontal position and fi xed so that they
do not move during casting. The installation frames must be positioned so that their upper surface is 30
mm above the fi nished fl oor surface. The junction of the installation frame and fl oor is fi lled with fl ooring
material or silicone mastic. To achieve the best result regarding tightness, the installation frame should
be fi lled up to the top level e.g. with acrylic fi ller
after the installation
. The main points concerning the
installation of the subsurface frame are shown in the picture below.
1. Installation frame
2. Concrete casting
3. Finished fl oor surface
4. Silicone mastic
5. Acrylic fi ller
Place the kettle on the installation frame and adjust to a horizontal position with the adjusting bolts
which are in the corners of the pillars. When the kettle is in a horizontal position, it must be fi xed to the
installation frames with the help of M12 fi xing bolts. The control pillar has 4 bolts and the support pillar
has 2 bolts. Tighten the adjusting nuts carefully. Do not seal the space between the kettle pillars and
installation frame as there must be enough change of air.
Содержание PROVENO E
Страница 4: ...4 PROVENO E Rev 1 2 24 08 2016 ...
Страница 68: ...68 PROVENO E Rev 1 2 24 08 2016 Technical specifications 8 Technical specifications ...
Страница 71: ... 71 PROVENO E Rev 1 2 24 08 2016 Technical specifications ...
Страница 72: ......