SAFETY INFORMATION
CD25
2-24
Published 1-06-2017 Control # 579-01
2-24
Most overhead power lines
are not
insulated. Treat all
overhead power lines as being energized unless you have
reliable information to the contrary from the utility company
or owner.
The rules in this
Operator Manual
must be followed at all
times, even if the electrical power lines or equipment have
been de-energized.
The safest way to avoid electrocution is to stay away from
electrical power lines and electrical power sources.
It is not always necessary to contact a power line or power
source to become electrocuted. Electricity, depending on
magnitude, can arc or jump to any part of the load, load line,
or crane boom if it comes too close to an electrical power
source. Low voltages can also be dangerous.
Set-Up and Operation
During crane use, assume that every line is energized (“hot”
or “live”) and take the necessary precautions.
Set up the crane in a position such that the load, boom, or
any part of the crane and its attachments cannot be moved to
within 6 m (20 ft) of electrical power lines or equipment. This
includes the crane boom (fully extended to maximum height,
radius, and length) and all attachments (jibs, rigging, loads,
etc.). Overhead lines tend to blow in the wind so allow for
lines’ movement when determining safe operating distance.
A suitable barricade should be erected to physically restrain
the crane and all attachments (including the load) from
entering into an unsafe distance from electrical power lines
or equipment.
Plan ahead and always plan a safe route before traveling
under power lines. Rider poles should be erected on each
side of a crossing to assure sufficient clearance is
maintained.
United States OSHA regulations require a flagman when
operating in close proximity to energized power lines.
Appoint a reliable and qualified signal person, equipped with
a loud signal whistle or horn and voice communication
equipment, to warn the operator when any part of the crane
or load moves near a power source. This person should
have no other duties while the crane is working.
Tag lines should always be made of non-conductive
materials. Any tag line that is wet or dirty can conduct
electricity.
Do not
store materials under power lines or close to
electrical power sources.
Electrocution Hazard Devices
The use of insulated links, insulated boom cages/guards,
proximity warning devices, or mechanical limit stops does
not assure that electrical contact will not occur. Even if codes
or regulations require the use of such devices, failure to
follow the rules listed here may result in serious injury or
death. You should be aware that such devices have
limitations and you should follow the rules and precautions
outlined in this manual at all times even if the crane is
equipped with these devices.
Insulating links installed into the load line afford limited
protection from electrocution hazards. Links are limited in
their lifting abilities, insulating properties, and other
properties that affect their performance. Moisture, dust, dirt,
oils, and other contaminants can cause a link to conduct
electricity. Due to their capacity ratings, some links are not
effective for large cranes and/or high voltages/currents.
The only protection that may be afforded by an insulated link
is below the link (electrically downstream), provided the link
has been kept clean, free of contamination, has not been
scratched or damaged, and is periodically tested (just before
use) for its dielectric integrity.
Boom cages and boom guards afford limited protection from
electrocution hazards. They are designed to cover only the
boom nose and a small portion of the boom. Performance of
boom cages and boom guards is limited by their physical
size, insulating characteristics, and operating environment
(e.g. dust, dirt, moisture, etc.). The insulating characteristics
of these devices can be compromised if not kept clean, free
of contamination, and undamaged.
Proximity sensing and warning devices are available in
different types. Some use boom nose (localized) sensors
and others use full boom length sensors. No warning may be
given for components, cables, loads, and other attachments
located outside of the sensing area. Much reliance is placed
upon you, the operator, in selecting and properly setting the
sensitivity of these devices.
Never rely solely on a device to protect you and your fellow
workers from danger.
Some variables you must know and understand are:
FIGURE 2-5
Reference Only
Содержание CD25
Страница 5: ...Operator Manual CD25 R e f e r e n c e O n l y ...
Страница 6: ...R e f e r e n c e O n l y ...
Страница 14: ...TABLE OF CONTENTS CD25 OPERATOR MANUAL TOC 6 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 18: ...INTRODUCTION CD25 1 4 Published 1 06 2017 Control 579 01 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 55: ...2 37 CD25 SAFETY INFORMATION 2 Published 1 06 2017 Control 579 01 8496 1 FIGURE 2 10 R e f e r e n c e O n l y ...
Страница 66: ...SAFETY INFORMATION CD25 2 48 Published 1 06 2017 Control 579 01 2 48 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 100: ...CAPACITY CHART CD25 4 4 Published 1 06 2017 Control 579 01 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 150: ...MAINTENANCE CD25 6 40 Published 1 06 2017 Control 579 01 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 152: ...ADJUSTMENTS CD25 7 2 Published 1 06 2017 Control 579 01 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 156: ...8 4 SPECIFICATIONS CD25 Published 1 06 2017 Control 579 01 Boom angle Maximum 80 Minimum 0 R e f e r e n c e O n l y ...
Страница 159: ...R e f e r e n c e O n l y ...
Страница 160: ...R e f e r e n c e O n l y ...