Lucent Technologies Lineage
®
2000 400A, 60Hz Ferroresonant Rectifier J85503C-3
Issue 10 July 2000
Testing 6 - 11
Control (TR) Test
1. Press and hold the transfer rectifier (TR) switch on the test set for
5 seconds. The rectifier should turn off simulating a remote
shutdown from the controller. The TRH lamp on the test set should
light.
2. Release the switch. The rectifier should restart and the TRH lamp
should go out.
3. Reduce the test load to 0 amperes.
4. Press the HV switch on the test set. The rectifier should continue
to operate.
Selective High
Voltage Shutdown
(SHVSD) and
Restart
1. Adjust the test load so that the rectifier delivers 40-60A, 10 to 15
percent of its rated amperage.
2. Momentarily press the HV switch on the test set. The rectifier
should shut down, and the RFA LEDs on the control panel and on
the test set should light.
3. Momentarily press the RS switch on the test set. The rectifier
should restart and both RFA lamps should go off.
Float/Equalize Test
1. Adjust the load so that the rectifier delivers between 20 and 30
amperes.
2. Turn the Power switch Off.
3. Short TB2 terminals EQL and EQLR on CM4.
4. Turn the Power switch On. The equalize LED should light.
5. Use the Equal Adj potentiometer on the control panel to set the
voltage per the plant requirement (normally 2.0 volts above float
voltage).
6. Turn the Power switch Off.
7. Remove strap from TB2 on CM4 or return it to original setting.
8. Turn the Power switch On.