Lucent Technologies Lineage
®
2000 400A, 60Hz Ferroresonant Rectifier J85503C-3
Issue 10 July 2000
Installation 5 - 11
AC Power Cables
Use Figures 5-3 and 5-4 as references for this section. Observe all
precautions in Section 4.
1. Disconnect ac power from ac distribution service panel that
supplies power to the rectifier.
2. Install three fuse holders (one for each phase) or one circuit
breaker for the rectifier in the ac service panel. Leave circuit
breaker in off position or leave fuses out.
3. Install three phase leads and ac ground (AC EG) at service panel
and route conductors to rectifier.
4. Install crimp connectors onto phase leads and AC EG lead as
required by plant installation. Use the proper crimping tool and die
for the connector to prevent damage to equipment. (See Table
5-A.)
5. Secure phase leads and AC EG lead in rectifier. Install ground
lead first. Torque phase connections as follows:
List 1 and 2
65 in-lbs (8 Nm)
List 3 and 4
30 in-lbs (4 Nm)
AC EG
30 in-lbs (4 Nm)
6. Verify that the branch circuit breaker to the rectifier in the ac
service panel is off or fuses are removed. Reenergize ac service
panel. Tag branch circuit breaker or fuse holders to inform others
not to close (turn on) the breaker or insert fuses. If the branch
circuit is protected by fuses, physically remove the fuses from the
area of the ac distribution service panel.