Review the Plan With the Customer
85
Review the Plan With the Customer
30 days prior to solution delivery date, the Hewlett-Packard Site Preparation Specialist will verify that the
site meets or exceeds the system requirements and specifications. At this time, the Site Preparation
Specialist and the customer should again review the site survey checklist with particular attention to the
following items:
•
Power needs. Verify that the required dedicated circuits are available. Verify that the required cables,
plugs, and receptacles have been ordered. Verify that grounding requirements have been met.
•
Space needs. Verify that sufficient space exists for uncrating and installing the equipment. Verify that
serviceability space has been included in the floor layouts.
•
Cooling needs. Verify that the customer site air conditioning meets the requirements for rp7400 systems.
Verify that the configuration of the system cabinets does not create air temperature problems for
surrounding equipment.
•
Utility needs. Verify that requirements for phone lines, lighting, etc., have been incorporated in the layout
plans.
Sites failing to meet the system requirements and specifications by the scheduled solution delivery date may
have their installation date postponed.
Содержание rp7400
Страница 1: ...rp7400 Hardware Manual ...
Страница 4: ...What s New 4 ...
Страница 6: ...System Overview 6 ...
Страница 15: ...rp7400 Enterprise Server System Safety and Regulatory Information 15 ...
Страница 16: ...rp7400 Enterprise Server System Safety and Regulatory Information 16 ...
Страница 17: ...rp7400 Enterprise Server System Safety and Regulatory Information 17 ...
Страница 18: ...rp7400 Enterprise Server System Safety and Regulatory Information 18 Declaration of Conformity ...
Страница 22: ...rp7400 Enterprise Server System Safety and Regulatory Information 22 ...
Страница 24: ...Review the Sales Order 24 ...
Страница 26: ...Plan the Site Visit 26 ...
Страница 28: ...Visit the Site 28 ...
Страница 32: ...Review HP Responsibilities 32 ...
Страница 36: ...Develop the Schedule 36 ...
Страница 38: ...Specify the Space for Unpacking 38 ...
Страница 44: ...Specify Hard Floor Requirements 44 ...
Страница 52: ...Specify the System Requirements 52 ...
Страница 56: ...Determine the ESD Requirements 56 ...
Страница 58: ...Determine the Acoustic Requirements 58 ...
Страница 60: ...Determine RFI Requirements 60 ...
Страница 62: ...Review Local Codes 62 ...
Страница 64: ...Determine Altitude Requirements 64 ...
Страница 68: ...Identify Sources of Electrical Interference 68 ...
Страница 70: ...Identify Other Environmental Influences 70 ...
Страница 72: ...Identify Telephone Requirements and Define Remote Access 72 ...
Страница 74: ...Identify Special Network Requirements 74 ...
Страница 76: ...Determine Service Access Needs 76 ...
Страница 78: ...Determine Fire Protection Requirements 78 ...
Страница 80: ...Define E Stop Requirements 80 ...
Страница 82: ...Determine Other Needs 82 ...
Страница 84: ...Generate the Plan 84 ...
Страница 86: ...Review the Plan With the Customer 86 ...
Страница 88: ...Execute the Site Plan 88 ...
Страница 94: ...Console Cable Connections 94 ...
Страница 96: ...HP 700 Series System Console Configuration 96 ...
Страница 100: ...Core I O Connections and Indicators 100 ...
Страница 104: ...Secure Web Console Installation 104 ...
Страница 106: ...LAN Console 106 ...
Страница 108: ...PC Direct Connect as System Console 108 ...
Страница 114: ...SCSI Devices 114 ...
Страница 118: ...Cable Management 118 ...
Страница 124: ...Cabinet Extension Kit 124 ...
Страница 134: ...rp7400 Server Boot up 134 ...
Страница 136: ...Accessing Guardian Service Processor Internal Port 136 ...
Страница 142: ...Chapter Shutting Down the SPU Shutting Down the SPU 2 ...
Страница 148: ...Adding a Disk Drive to an HP UX System 146 ...
Страница 162: ...Add I O Cards 160 ...