Page 77
5. ZERO and SPAN CALIBRATION:
Go to Operation, Reagents Setup, Install New Reagents menu, confirm the menu items and select
the “START NEW REAGENT CYCLE” function for the BioTector to prime the reagents and set the
Zero Adjust (zero offset) values automatically. See Section
_____
Observe that the automatic pressure/flow test passes when analyzer is started up. See Section
_____
It is recommended to check the zero response. When the Zero Calibration cycle is completed, go
to Operation, Start Stop menu (see Section
analyzer. Go to Zero Calibration menu and select RUN ZERO CHECK function. Alternatively, to
confirm that the zero response is correct, connect DIW to the manual sample port and run 5
analysis cycles on DIW using the Manual Program menu.
(
If manual port is not available, use the input
point for SAMPLE 1.
If the BioTector has been in storage for a long period, and if the zero readings are not
satisfactory,
a second “Install New Reagents” cycle may be required.)
_____
If the zero readings and CO
2
peaks are correct, items from 1 to 6 below can be skipped.
_____
1
Confirm that the pH in the reactor is correct, using the test sequence in the pH Test menu. See
Section
_____
2
Check for a pH of <2 during the TIC phase.
_____
3
Check for a pH of >12 during the Base Oxidation phase.
_____
4
Check for a pH of <2 during the TOC phase.
_____
5
Run a further 2 reactions on DIW.
_____
6
Run an “Install New Reagents” cycle on the system to adjust the zero offset.
_____
Program the concentration of the available standard solution in the Span Calibration menu.
(To
prepare a standard solution, see procedures described in Section
sheet “R009. Standard Solutions for BioTector Multi-component Analyzer”, which is available inside the
MMC/SD card shipped with the BioTector.)
_____
Connect the standard solution to the MANUAL/CALIBRATION port. If these ports are not
available, use the SAMPLE 1 port. It is recommended that the standard solution should be located
at the same height as the sample chamber. Run the Span Calibration cycle using the RUN SPAN
CALIBRATION function in Span Calibration menu. A minimum of five complete analysis cycles is
recommended for the span calibration.
_____
Download BioTector “All Data” in text format into the MMC/SD card using the SEND ALL DATA
function in Data Output menu to record all changes made in the system configuration. See Section
_____
Go to Start Stop menu and start the BioTector. When the BioTector is running online, carefully
observe the first two or three reactions and confirm that the CO
2
peaks are correct.
_____
Содержание BioTector B3500C
Страница 17: ...Page 17 Software Menu Diagram...
Страница 44: ...Page 44 Figure 4 BioTector analysis layout typical TIC TOC system...
Страница 46: ...Page 46 Figure 6 BioTector oxygen concentrator layout...
Страница 63: ...Page 63...
Страница 78: ...Page 78 Section 8 Maintenance Menu Maintenance Menu Diagram...
Страница 155: ...Page 155 Section 11 System Replacement and Spare Parts...
Страница 163: ...Page 163 ZK Zero check ZM Manually input zero adjust ZS Zero and Span...