Chapter V GW4D20 / GW4D20B Turbocharged Diesel Engine
Great Wall Baoding Internal Combustion Engine
Manufacturing Company Limited
383
Fig. 5-20-52 Installing the engine bracket
fastening nuts
Fig. 5-20-53 Installing the transmission
assembly
Attention:
During the installation of engine, do not
damage the oil pipe, electric elements and sensor etc.
Installing the transmission assembly
①
(1) Install the transmission dowel pins: Fit the 2
transmission dowel pins into the back end face of the
cylinder head by a special tool; there should be no
deflection or improper mounting.
(2) Install the transmission assembly. Screw down the
fastening bolts connecting the transmission and the
clutch in proper order and as per specified torque in
several times. See Fig. 5-20-53.
(3) Install the drive shaft.
After the installation, carry out the following operations:
(1) Connect the earthing cable of storage battery.
(2) Fill coolant into the cooling system.
(3) Fill the lubricating oil in the lubrication system.
(4) Start the engine and check it for normal working, and
check the cooling system and the lubrication system for
leakage.
Transmission
Clutch assembly