Inspection and Unpacking
Liebert
®
CRV
™
14
3.3
Moving the Unit Using Rigging—600mm (24") Models
1. Use a pallet jack or forklift to raise the packaged unit.
2. Place slings under the skid runners, equally spacing the slings to make sure the unit is balanced
(see
).
3. Lower the unit and remove the pallet jack or forklift.
4. Connect the slings to the lifting device, using spreader bars or similar equipment to protect the
unit (see
).
5. Move the unit to its installation location. Two or more properly trained and qualified personnel
are required to move the Liebert CRV to its installation location.
6. Lower the Liebert CRV and remove the slings.
Figure 8
Moving the unit using rigging
!
WARNING
Risk of top-heavy unit falling over. Can cause equipment damage, injury and death.
Verify that all lifting equipment is rated for the weight of the unit. See
for
unit weights.
Read all of the following instructions before attempting to move, lift or remove packaging
from the Liebert CRV.
!
CAUTION
Risk of sharp edges, splinters and exposed fasteners. Can cause injury.
Only properly trained and qualified personnel wearing appropriate safety headgear, gloves,
shoes and glasses should attempt to move, lift or remove packaging from the Liebert CRV or
prepare the unit for installation.
NOTE
Wrapping one or two more straps around the middle of the Liebert CRV will improve stability
when it is lifted.
197023
Rev. 5