UPServer2.0
ON-LINE DOUBLE CONVERSION
Figura 21
The Installation for baffle of battery pack
4. Grasp the handle in front of the battery pack, take out of it and hold it, then remove the battery
pack as fig. 27 shown.
Figura 22 Rimozione pacco batterie
5.Hold the middle of the new battery pack, insert it. Once install the new battery pack, make sure it is
completely inserted into the chassis as fig 23 shown
Figure 23
Installation
for battery
pack
Testing New Batteries
To test new batteries:
1. Plug the UPS into a power outlet for 48 hours to charge the
batteries.
2. Start up the UPS by pressing the start up combination button.
3. Press the battery test combination button to activate the battery test.
The UPS starts a battery test if the batteries are fully charged, the
UPS is in Normal mode with no active alarms, and the bypass
voltage is acceptable.
During the battery test, the UPS transfers to Battery mode and
discharges the batteries for 10 seconds. The LED indicators of the front cover
stop cycling when the test is completed.