Equipment Installation
XDM-300 Installation and
Maintenance Manual
3-38 ECI
Telecom
Ltd.
Proprietary
417006-2311-0H3-A00
5.
Route the fiber ends through the cable guides to the splice support area.
6.
Identify the adapter panel pigtail to be spliced to each user fiber.
7.
Insert splicing sleeves over the pigtail, splice the user fiber to the pigtail,
and slide the splicing sleeve over the splice.
8.
Place the splicing sleeve in one of the slots in the splice support.
N
OTE
:
When more than 12 fibers are connected to the ODF,
first start filling the slots of the lower splice support. After the
slots are occupied, reinstall the top splice support and
continue filling the support slots.
9.
After splicing all the fibers, reinstall the protective cover removed in Step
3.
10.
Push the swing-out tray back into the unit.
11.
Close the ODF front cover by pushing it up till it clicks to the unit.
12.
Refer to Attaching rack mount brackets (on page
) and secure the user
fibers with cable ties to the fiber fastening bracket at the rear of the ODF.
C
AUTION
:
To prevent damage to fibers, do not tighten the
cable ties.
To install ODF units in a rack:
|
Install each ODF in the prescribed rack position and fasten it to the rack
side rails with four screws.
Содержание XDM-300
Страница 1: ...XDM 300 Installation and Maintenance Manual Version 7 417006 2311 0H3 A00...
Страница 2: ......
Страница 8: ......
Страница 24: ...Introduction XDM 300 Installation and Maintenance Manual 1 8 ECI Telecom Ltd Proprietary 417006 2311 0H3 A00...