Before You Start
XDM-300 Installation and
Maintenance Manual
2-2 ECI
Telecom
Ltd.
Proprietary
417006-2311-0H3-A00
3.
Prepare transmission cables at the installation site.
4.
Route the required power, alarm, management, and transmission cables to
the intended XDM-300 equipment location (see "
"
on page
5.
If required, install the equipment racks (see "
" on page
6.
Mark the location of each XDM-300 shelf and relevant accessories Fiber
Storage Tray (FST), patch panels, and Optical Distribution Frame (ODF)
on each rack, in accordance with the site installation plan.
N
OTE
:
If you are currently installing an XDM-300 shelf
without TPU protection, you may want to leave sufficient
space above/under the shelf to enable the addition of the
TPU/TPUs at a later stage.
7.
When applicable, install the EMS-XDM management station (see the
EMS-XDM User Manual).
8.
Install the power distribution and alarm panels – xRAP-B (on page
) or
xRAP-100 (on page
), and other equipment needed in each rack.
9.
Install the XDM-300 shelves in the appropriate rack.
10.
For each XDM-300 shelf where optical modules are used, install an FST
above the XDM-300 shelf and route the optical fibers to the FST (see
"
" on page
N
OTE
:
Even if you are not currently installing an FST, it is
recommended that you leave enough space above the
XDM-300 shelf to enable future installation, in case optical
modules are added to the shelf at a later stage.
11.
Install the ECU300/ECU300-F, FCU300, MXC300, and I/O cards in the
shelf (see "
" on page
).
12.
Install the prescribed I/O modules in the shelf.
13.
If applicable, install the TC card and the prescribed TPMs in the TPU.
Содержание XDM-300
Страница 1: ...XDM 300 Installation and Maintenance Manual Version 7 417006 2311 0H3 A00...
Страница 2: ......
Страница 8: ......
Страница 24: ...Introduction XDM 300 Installation and Maintenance Manual 1 8 ECI Telecom Ltd Proprietary 417006 2311 0H3 A00...