Horizontal assembly
User Information
Load-bearing tower Staxo 40
Erecting further storeys
Note:
Do not pre-assemble units any higher than 11
m.
➤
Fit a Staxo 40 coupler and push the next frame onto
it.
➤
Use Staxo 40 tube connectors D48.3mm to make
crane-handling-safe links between the frames at
every joint.
➤
Fit and secure diagonal crosses in the same way as
in the first 'storey'.
➤
Install scaffold planking units where needed
➤
Close the anti-liftout guard.
Optionally: Railings on the top 'storey'
To meet very stringent safety requirements, 'mounted-
ahead' railings can be fitted in the top section.
This is done in line with the instructions given in
'Assembling towers in the upright with 'mounted-ahead'
railings'.
➤
Mount the Staxo side railings and secure them with
a Spring locked connecting pin 16mm to prevent
accidental lift-out.
Close-up 1
➤
Mount Staxo front railings and secure them with a
Spring cotter
5mm to prevent accidental lift-out.
Close-ups 2 and 3
98024-215-01
98024-215-02
98024-296-01
L
Staxo side railing
M
Staxo front railing
N
Spring locked connecting pin 16mm
O
Spring cotter 5mm
L
L
M
M
1
2
3
9
-01
8024-325
N
980 - -02
24
325
O
98024-325-03
98024-325-04